Kona Mega gateway installation Field procedure for mounting, grounding, cabling, powering and commissioning a TEKTELIC Kona Mega LoRaWAN gateway serving electric, gas and water meters.

elec gas water pit Internet ISP router Antennas above clutter 80 cm keep-outaround radiating antennas Crossarm at the top:Antennas at the top:antennas 6–20 ft apart Sentry 250 at the basepower, PoE and network Structure rated ≥ 136 kg (300 lb) Keep box Gateway kit, antenna kit,Sentry 250 components Gateway on the bench Ground stake PoE inj. PoE: data + power LAN AC in Ethernet to internet Call Vision Metering (803) 628-0035 confirm it shows in VM diagnostics 8–5 ET, Mon–Fri On the ground: internet test 4 × M6 boltsone orientation onlyBulkhead faces down Kona Megabelow the crossarmbelow the antennas #10 AWG min, straight runto ground bar and rod Ant 0, longer Ant 1, shorter GPS 6–20 ft apart Ant 0, longer Ant 1, shorterside arm GPS 6 ft coax, gentle bends Drip loops N-type, 15–20 in·lb Vinyl, mastic, vinylvent left clear Sentry 250 DRC PoE DPR Battery (optional) 5 × M5 + 1 × M6 240 VAC feed Network to DPR “Line” Breaker open Outdoor PoE SPDbeneath gateway “Equip + PoE” cabledown to Sentry 250 GPS time LED greenflashing, then solid ID tag: EUI, date, crew
Showing the full printable guideThis viewer has interactive features turned off, so every step is listed below for the default setup (PoE, copper Ethernet, crossarm, Option 4). For the interactive version with model options, the bulkhead trainer and the RF budget, save the attachment and open it in Chrome: in the Files app, choose Open with, then Chrome.
Step 1 of 16

Plan the site

Put the antennas above local clutter with clear sight lines toward the meters, on a structure the public cannot reach, with power and network available at its base.

  1. Survey the meter mix. Electric meters sit on house walls near 1.5 m, gas near 1 m, and water meters are often in pits under lids. Pit meters usually define the coverage edge, so plan for them.
  2. Choose a pole, water tower, substation structure or rooftop able to carry a dead load of at least 136 kg (300 lb).
  3. Plan a crossarm at the top: two LoRa antennas at least 6 ft and no more than 20 ft apart, the GPS antenna on the arm, and the gateway just below it.
  4. Keep antennas away from overhead power lines and other electric light or power circuits, and plan the work so nothing can touch them. Contact can cause serious injury or death.
  5. Confirm the location is restricted access. The enclosure can reach 90 °C in high ambient and must not be touchable by non-service persons.
  6. Plan for at least 80 cm (31.5 in) between radiating antennas and any person. That FCC exposure condition assumes no co-located transmitters; shared structures need their own RF exposure evaluation.
  7. Plan the Sentry 250 at the base: a 240 V feed to its breaker, the site network to its DPR protector, and one PoE Ethernet cable up to an outdoor PoE surge protector beneath the gateway.
  8. Locate the site ground system, or plan a ground rod and bonding per NEC and local code.
Qualified personnel onlyInstallation, operation and maintenance must be done by a trained service technician aware of all hazards, following local and national electrical codes.
LightningNever work on the system during lightning activity.
Antenna spacing6–20 ft
Structure dead load≥ 136 kg (300 lb)
Operating range−40 to 60 °C incl. solar, up to 4,000 m
Step 2 of 16

Unpack and inspect

Check every kit and capture the gateway’s identity on the ground, where it is easy.

  1. Gateway kit: Kona Mega gateway, mounting bracket, field-installed power cable adaptor, field-installed Ethernet cable adaptor, 4 × M6×1.0 × 14 mm bolts with washers and lock washers, and a 1 m ground cable.
  2. Antenna kit: two LoRa antennas (one longer, one shorter) and two 6 ft coax cables.
  3. Sentry 250 kit: Meanwell DRC-100A power supply, Procet PoE injector, DPR shielded PoE protector, circuit breaker, outdoor PoE surge protector, and an optional SigmasTek SP12-55 battery.
  4. Site supplied: 4 × M8 bolts (wall) or 2 pipe clamps (pole) for the gateway, 5 × M5 bolts and 1 × M6 bolt for the Sentry 250, and Ethernet cables.
  5. Inspect the cartons, report significant damage to TEKTELIC, and keep the gateway box and foam for any return.
  6. Photograph the label and record the serial number, MAC address (begins 64:7F:DA) and gateway ID (EUI-64).
  7. Lay out the tools: metric 6-point sockets and torque wrench, anti-oxidant compound, small wire brush, clean cloth, and a weatherproofing kit (Scotch WK-101 recommended).
No field-serviceable partsNever open the gateway enclosure. Only an approved TEKTELIC service center may open it.
Gateway weight5.1 kg (11.3 lb)
Step 3 of 16

Test connectivity on the ground

Prove the gateway reaches the internet and shows up in Vision Metering diagnostics before it goes up the structure.

  1. Set the gateway on a clean, dry surface. LoRa and GPS antennas are not needed for this test. Connect the supplied ground cable to the 2-hole lug and a ground point first.
  2. Run an Ethernet cable from the gateway’s Ethernet port to the PoE injector’s “Equip + PoE” port, and a second cable from the injector’s network port to the internet source, such as the site router or a cellular hotspot.
  3. Power the PoE injector last; it powers the gateway over the same Ethernet cable that carries its data.
  4. Allow up to 2 minutes to boot, or up to 15 minutes if a software upgrade runs.
  5. Schedule the test within Vision Metering hours (8 AM–5 PM Eastern, Monday–Friday). Call Vision Metering at (803) 628-0035 with the gateway ID (EUI-64) and serial number, and confirm the gateway shows up in Vision Metering diagnostics. Do not mount the gateway until it does.
  6. Power down, then disconnect in reverse order: power, backhaul, ground last.
Verify before you climbA gateway that fails this test is far easier to troubleshoot or swap on the ground than on the structure.
Boot time< 2 min typical, up to 15 min after upgrade
Vision Metering
Phone: (803) 628-0035
Gateway email: john@visionmetering.com
Hours: 8 AM–5 PM Eastern, Monday–Friday
Step 4 of 16

Fit the bracket

Attach the mounting bracket to the back of the gateway before lifting.

  1. Seat the bracket’s 4 protrusions in the back of the gateway; they let it fit in only one orientation.
  2. Bolt it on with the four supplied M6×1.0 × 14 mm bolts, each with a flat washer and a lock washer.
  3. Check that the connector bulkhead will face down, toward earth.
Bracket bolts4 × M6×1.0 − 14 mm with washers
Step 5 of 16

Mount the gateway

Secure the gateway just below the antennas with the bulkhead pointing at the ground.

  1. Pole: support the unit temporarily and fit two site-supplied pipe clamps, one through the upper and one through the lower slotted clamp points.
  2. Wall: set two M8 bolts at 139.7 mm (5.5 in) centers with heads standing 2 mm off the wall. Hang the bracket keyholes on them and tighten, then add two M8 bolts through the bottom holes.
  3. Keep the area below the bulkhead free of obstructions so the cables can drop straight down.
Red: wall anchor points (top keyholes, bottom holes, M8 bolts). Blue: pole clamp slots (2 pipe clamps). The 4 protrusions on the bracket fit the gateway one way only.
Mount before cablingThe gateway must be securely mounted before any cable is connected or the unit is operated.
Wall bolts4 × M8, keyholes at 139.7 mm (5.5 in)
Pole2 pipe clamps
Step 6 of 16

Ground it first

The protective earth ground is mandatory and is always the first connection to the gateway.

  1. Lightly abrade the casting ground area with a fine wire brush to remove oxide.
  2. Wipe away debris with a clean cloth.
  3. Immediately coat the contact surface with a thin layer of anti-oxidant compound.
  4. Fit the supplied 1 m ground cable’s 2-hole lug with the two supplied 1/4-20 × 1/2 in bolts, flat and star lock washers, torqued to 10.4 N·m (92 in·lb).
  5. Run at least #10 AWG to the site ground system per local and national code. Keep it short and direct; in lightning-prone sites minimize connection inductance and ground-bed resistance.
Ground before anything elseThe primary surge protectors on the DC, Ethernet, GPS and LoRa ports can bridge the isolation boundary during over-voltage. The ground must be in place before any other interface is connected.
Conductor#10 AWG minimum
Lug2-hole, 1/4 in × 0.75 in
Torque10.4 N·m (92 in·lb)
Step 7 of 16

Mount the antennas

Two LoRa antennas at the top of the structure, 6 to 20 ft apart, with the GPS antenna in open sky.

  1. Mount both LoRa antennas vertically at the ends of the crossarm, at least 6 ft and no more than 20 ft apart. The longer antenna connects to Ant 0 (port 0), the shorter to Ant 1 (port 1).
  2. Mount the active GPS antenna on the crossarm with an unobstructed view of the sky (the port supplies 5 V DC, 50 mA max). GPS provides network timing and geolocation.
  3. Stay clear of overhead power lines and other electric circuits while lifting and fixing the antennas.
  4. Ground the antenna mounts as national and local codes require.
Power linesNever let an antenna, crossarm or cable come near energized lines.
Antenna spacing6 ft min, 20 ft max
Port 0longer antenna
Port 1shorter antenna
Step 8 of 16

Run the coax

Short cables in gentle bends, secured, and dripping before they reach the gateway.

  1. Connect each antenna to the gateway with its supplied 6 ft coax cable.
  2. Route every cable in gentle bends. Sharp bends can break the cable, letting in water and corrosion and degrading reception.
  3. Replace any cable showing crimping along the insulation. If the connector nut can be pulled off the cable, it was bent too far and must be replaced.
  4. Secure the cables to the antenna mounts and structure with UV-rated ties, leaving a drip loop below the bulkhead (general practice).
  5. Label every cable at both ends: Ant 0, Ant 1, GPS.
  6. Where code calls for coax lightning protection, the Vision Metering references list the L-com AL-NMNFB N-type protector.
Coax2 × 6 ft, supplied
Step 9 of 16

Connect RF

Mate each antenna cable to its N-type port and torque it.

  1. Connect GPS, Ant 0, Ant 1 to the N-type female ports on the bulkhead: the longer antenna to Ant 0, the shorter to Ant 1.
  2. Thread by hand, then torque to 1.7–2.3 N·m (15–20 in·lb).
  3. Give every LoRa port an antenna or a 50 Ω termination before power is applied, since both ports can transmit (general practice).
N-type torque1.7–2.3 N·m (15–20 in·lb)
Impedance50 Ω
Step 10 of 16

Weatherproof

Mated N-type connections are not waterproof on their own. Tape each one in three layers, cap everything unused, and leave the vent alone.

  1. Layer 1: after connecting the cable, wrap one layer of 3/4 in (19 mm) vinyl tape starting 1 in (25 mm) beyond the connector, past the clamping nut but short of the base.
  2. Layer 2: cut butyl mastic tape long enough to run lengthwise from 2 in (51 mm) beyond layer 1 to the base. Use more pieces as needed for complete coverage.
  3. Layer 3: wrap one half-lapped layer of 2 in vinyl tape from 1 in below the mastic to the base, then apply a second layer.
  4. Close every unused Ethernet, DC or hybrid connector with its supplied protective cap. Unmated RF ports are waterproof by design.
  5. Do not cover the enclosure vent (general practice).
base nut 1 in 1 ¾ in vinyl, one layer 2 butyl mastic, lengthwise 3 2 in vinyl, half-lapped, 2 layers
Bars show how far each layer extends from the base. Layer 1 starts 1 in (25 mm) past the connector and stops short of the base. The mastic runs 2 in (51 mm) beyond layer 1 to the base. Layer 3 starts 1 in below the mastic.
Tape kitScotch WK-101 recommended
Step 11 of 16

Mount the Sentry 250

Hang the Sentry 250 power and network box at the base of the structure.

  1. Choose an anchor point at the base with access to the site power feed and the site network.
  2. Install a site-supplied M5 (or 10-32) bolt at the anchor point, leaving the head 2 mm from the surface.
  3. Hang the Sentry 250 by the keyhole slot at its top and tighten the bolt.
  4. Insert and tighten four more M5 (or 10-32) bolts through the holes on the top and bottom of the box, and an M6 (or 1/4-28) bolt through the lower keyhole slot.
  5. Connect the Sentry 250 ground to the site ground system before any other connection.
Ground every piece firstThe ground connection of each piece of equipment is made before any other interface.
Bolts5 × M5 (10-32) + 1 × M6 (1/4-28)
Step 12 of 16

Wire the Sentry 250

Bring power and network in through the Sentry 250’s three bottom ports, with the breaker open.

  1. Decide how to use the three bottom ports for the site: input power, input network and output PoE.
  2. With the feed de-energized, connect the 240 V site supply (L1, L2) to the 6 A circuit breaker inside the Sentry 250. Leave the breaker open.
  3. The breaker outputs feed the Meanwell DRC-100A AC input (L, N); its ground terminal goes to earth. The DRC-100A V+ and V− outputs feed the Procet PoE injector + and −.
  4. If fitting battery backup, place the SigmasTek SP12-55 in the housing and connect it to the DRC-100A BATT + and − terminals.
  5. Connect the site network Ethernet cable to the DPR shielded PoE protector jack labeled “Line”, and the DPR’s equipment side to the Procet injector’s network input.
  6. Insert the tower Ethernet cable into the Procet jack labeled “Equip + PoE”.
240 V L1L2 CB6 A DRC-100A BATT + −V+ V−NL⏚ ground Battery (optional)SigmasTek SP12-55 ProcetPoE DPRPoE protector site network → “Line” network in “Equip + PoE” up the tower
Schematic only, after the Vision Metering installation guide. Breaker outputs feed the DRC-100A AC input; its DC output powers the Procet injector; the optional battery connects to the DRC-100A BATT terminals.
240 VOnly qualified personnel connect the site feed. Confirm it is de-energized before wiring (general practice).
Breaker2-pole, 6 A
SupplyMeanwell DRC-100A
Network protectorDPR shielded PoE protector (Transtector)
Step 13 of 16

Run the tower cable

Connect the gateway to the Sentry 250 through an outdoor PoE surge protector mounted beneath the gateway.

  1. Run the “Equip + PoE” cable from the Sentry 250 up the structure to the outdoor PoE surge protector beneath the gateway, then into the gateway Ethernet port with the field-installed Ethernet cable adaptor (watertight CPC RJ-45).
  2. The outdoor PoE surge protector carries PoE to the gateway, so it must be rated for 802.3bt on all four pairs (Procet lists PT-PR01G-OT at 60 W and PT-PR01GB-OT at 100 W).
  3. Bond the outdoor surge protector to the ground system with a short, direct conductor; a surge protector with no ground path protects nothing (general practice).
  4. Secure the cable down the structure with UV-rated ties and leave a drip loop at each end (general practice).
  5. If Ethernet is used only for commissioning, refit the protective cap afterward.
Ethernet cable≥ 24 AWG, outdoor rated
Step 14 of 16

Apply power last

Power goes on only after the ground, every antenna, every seal and the tower cable are done.

  1. Close the circuit breaker in the Sentry 250 last. The DRC-100A powers the Procet injector, which feeds the gateway over the tower cable. The PoE source must deliver IEEE 802.3bt Class 6 with Mode A and Mode B together; Microchip/Microsemi “GR” injectors will not work.
One power source onlyDirect DC and PoE must never be applied to the gateway at the same time.
External disconnectThe gateway has no disconnect device. The Sentry 250 breaker or another readily accessible device provides it.
Gateway power20 W typical, 40 W max
Step 15 of 16

Boot and verify

Watch it come up before leaving the site.

  1. Allow up to 2 minutes to boot, or up to 15 minutes if a software upgrade runs.
  2. Flashing green means initializing, no downlink sent in the last 10 minutes, or GPS unlocked for more than 24 hours. It turns solid green once the gateway transmits a downlink such as a Join Accept; power a meter or test device nearby to trigger one.
  3. Solid red is a fault: power-cycle, then contact Vision Metering at (803) 628-0035 if it persists.
  4. Call Vision Metering at (803) 628-0035 as soon as the gateway powers up (8 AM–5 PM Eastern, Monday–Friday; plan power-up inside those hours) and confirm it shows up in Vision Metering diagnostics. Do not leave the site until it does.
  5. Confirm GPS has a clear view of the sky.
Hot surfacesThe enclosure can reach 90 °C in high ambient.
Boot time< 2 min typical, up to 15 min after upgrade
Vision Metering
Phone: (803) 628-0035
Gateway email: john@visionmetering.com
Hours: 8 AM–5 PM Eastern, Monday–Friday
Step 16 of 16

Commission and document

Bring it into the network and leave a record the next crew can trust.

  1. Vision Metering completes commissioning and network registration.
  2. With Vision Metering, confirm meter uplinks are arriving and record an RSSI/SNR baseline for each meter type.
  3. Record the site details for Vision Metering: location, structure, antenna height, serial number and gateway ID. Photograph the antenna mounts and antennas, the gateway, the ground lug, each taped connector, the label, and the inside of the Sentry 250.
  4. Fit an ID tag on the structure with the gateway ID, date and crew (general practice).
Vision Metering
Phone: (803) 628-0035
Gateway email: john@visionmetering.com
Hours: 8 AM–5 PM Eastern, Monday–Friday

Make every connection in the right order

0faults
0/0required ports ready
Offgateway
    Gateway RF chain
    Meter population
    TypeTx dBmAnt dBiHeight mExtra loss dB

    Extra loss covers pit lids, meter glass and enclosures. Values here are planning placeholders; composite pit lids are commonly quoted at 10–20 dB and cast iron higher. Measure on site and override.

    Path loss: Okumura-Hata (valid 150–1500 MHz, base 30–200 m, mobile 1–10 m, 1–20 km), small/medium-city mobile correction, evaluated at 908.6 MHz uplink and 925.4 MHz downlink to match the NA Kona Mega’s 902–915 MHz receive and 923–928 MHz transmit bands. Hata gives the median loss; the fade margin covers location variability (about 10 dB for 90 % with 8 dB shadowing). Gateway sensitivity defaults scale TEKTELIC’s −142 dBm SF12 figure by the LoRa demodulation SNR limits (SF7 −7.5 dB to SF12 −20 dB). Meter sensitivity defaults are thermal noise over 500 kHz plus a 6 dB noise figure plus the same SNR limits. Receive diversity on Ant 1 is not credited, so two-antenna sites will do somewhat better on the uplink. Treat results as planning estimates and confirm with a drive test or propagation study.

    Torque and hardware card

    Ground lug, two 1/4-20 × 1/2 in bolts with flat + star washers10.4 N·m / 92 in·lb
    N-type RF connectors (LoRa, GPS, LTE)1.7–2.3 N·m / 15–20 in·lb
    Bracket to gateway4 × M6×1.0 − 14 mm
    Wall mount, keyhole spacing 139.7 mm (5.5 in), 2 mm head gap4 × M8
    Ground conductor#10 AWG min
    Ethernet conductors, outdoor-rated24 AWG min
    Sentry 250 mounting, top keyhole plus top and bottom holes, lower keyhole5 × M5 + 1 × M6
    Antenna spacing on the crossarm6–20 ft

    Vision Metering standard build

    1. Gateway Ethernet port, field-installed Ethernet cable adaptor
    2. Outdoor PoE surge protector beneath the gateway, bonded to ground
    3. Tower Ethernet cable down to the Sentry 250
    4. Procet PoE injector, jack “Equip + PoE”
    5. DPR shielded PoE protector, jack “Line”
    6. Site network (internet source)

    Power: 240 V (L1, L2) to a 6 A breaker, then the Meanwell DRC-100A, whose DC output powers the Procet injector. An optional SigmasTek SP12-55 battery connects to the DRC-100A BATT terminals. The outdoor surge protector carries PoE, so it must be rated for 802.3bt on all four pairs: Procet PT-PR01G-OT is listed at 60 W, PT-PR01GB-OT at 100 W.

    Tools and consumables

    1. Metric 6-point socket set and torque wrench
    2. Anti-oxidant compound (NO-OX-ID, Penetrox, Noalox, Ox-Gard)
    3. Small fine wire brush and clean cloth
    4. Scotch WK-101 wireless weatherproofing kit
    5. Pipe clamps sized to the pole, or four M8 bolts and anchors for the wall
    6. Five M5 (10-32) bolts and one M6 (1/4-28) bolt for the Sentry 250
    7. Ethernet cables; 3/4 in and 2 in vinyl tape and butyl mastic (or the WK-101 kit)

    Kit contents

    Gateway: Kona Mega, mounting bracket, field-installed power cable adaptor, field-installed Ethernet cable adaptor, 4 × M6×1.0 × 14 mm bolts with washers, 1 m ground cable.

    Antennas: 2 LoRa antennas (longer to Ant 0, shorter to Ant 1), 2 × 6 ft coax cables.

    Sentry 250: Meanwell DRC-100A, Procet PoE injector, DPR shielded PoE protector, circuit breaker, outdoor PoE surge protector, optional SigmasTek SP12-55 battery.

    Site supplied: 4 × M8 bolts (wall) or 2 pipe clamps (pole), 5 × M5 and 1 × M6 bolts (Sentry 250), Ethernet cables.

    Specifications

    Dimensions222.2 W × 101 D × 287.3 H mm UG; 222 × 268 × 101 mm datasheet 2026
    Weight5.1 kg (11.3 lb) UG; 5 kg datasheet
    EnclosureAluminium, UL Type 6 / IP67, no internal antennas
    Operating temperature−40 to 60 °C at sea level, including solar loading
    Humidity, altitude10–100 % condensing; −60 to 4,000 m
    Direct DC48 VDC nominal, 37–57 VDC operating after a 42 V maximum startup threshold; positive or negative ground referenced; SELV and LPS; overcurrent protection ≤ 10 A UG; source ≥ 1 A QSG
    PoEIEEE 802.3bt Class 6, Mode A and Mode B together, polarity insensitive; passive PoE 37–57 VDC also works PoE guide v12. Microchip/Microsemi “GR” injectors are not Class 5+ compliant and will not power a Mega. The 2023 user guide still lists 802.3at over four pairs.
    Power20 W typical datasheet; < 30 W typical, 40 W max PoE guide; 35 W max UG
    LoRa radio (current NA)Rx 902–915 MHz, Tx 923–928 MHz, frequency duplex, 64+8 Rx / 4 Tx, 2 × 27 dBm Tx, −142 dBm at SF12, NF 3.5 dB, Tx-Rx isolation 75 dB datasheet
    GPS portActive antenna; port supplies 5 V DC nominal, 50 mA max QSG
    Surge protectionPrimary on DC, Ethernet, GPS and LoRa ports. The 3G/4G antenna port is unprotected.
    Surface temperatureUp to 90 °C in high ambient
    RF exposure≥ 80 cm (31.5 in) from persons; the FCC condition assumes no co-located transmitters
    LoRa antenna (ISED, Canada)≤ 8 dBi with cable loss ≥ 0.5 dB (1 carrier, 28.5 dBm) or ≥ 2 dB (2 carriers, 30 dBm total)

    LED states

    OffNo power
    Flashing greenInitializing; or no downlink sent in the last 10 minutes; or GPS unlocked for more than 24 hours
    Solid greenPacket forwarder running, normal operation
    Solid redFault; power-cycle, then contact support if it persists

    Connectors

    InterfaceOn unitMate
    LoRa, GPS, cellular antennasN-type femaleN-type male
    Ethernet (CPC)Circular plastic threaded, RJ-45Chogori 33000111-02 or equiv.
    Ethernet (M12)M12 male, 8-contact, X-codedTE 2327989-1 or equiv.
    DC (CPC)Circular plastic, 2-contactChogori 23002211-02 or equiv.
    DC (M12)M12 male, 2-contact, A-codedTE T4111002021-000 or equiv.
    Hybrid optical / DCHarting hybridHarting-approved mate
    Earth ground1/4-20 UNC double hole2-hole lug, 1/4 in × 0.75 in

    US915 models

    CodeOptionLoRaDCLTEOptical
    T0004142Option 1, CPC1PoE onlyNoNo
    T0004470Option 2, CPC1CPCYesNo
    T0004537Option 3, CPC2CPCNoNo
    T0004250Option 4, CPC2CPCYesNo
    T0004251Option 5, hybrid optical1HybridNoYes
    T0004252Option 6, hybrid optical2HybridNoYes
    T0007208Option 2, M121M12YesNo
    T0007283Option 4, M122M12YesNo

    NA custom-channel-plan codes (T0005519, T0007752, T0007754) are omitted. The KONA Mega Gen3 (T0009468) received FCC certification in September 2026 and is not covered here.

    Sources

    1. TEKTELIC Kona Mega Gateway User Guide T0004279_UG v2.18, Dec 2023 (UG)
    2. TEKTELIC KONA Mega NA datasheet, Apr 2026
    3. TEKTELIC KONA Mega Quick Start Guide (QSG)
    4. TEKTELIC Gateway PoE Powering Guide v12
    5. TEKTELIC Kona Macro/Mega Antenna Selection Guide T0007323_ADG2
    6. Vision Metering, LoRa Gateway and Sentry 250 Installation Guide v3.0, Nov 2022
    7. Meanwell DRC-100A datasheet; Transtector DPR-F140 (DPR shielded PoE protector) datasheet; SigmasTek SP12-55IT spec and safety data sheets; L-com AL-NMNFB datasheet; 3M Scotch WK-101 instructions